Gantt chart: Lag and lead time, and end-to-start dependencies

Gantt chart: Lag and lead time, and end-to-start dependencies

When you add lag time, you delay the start time of the successor task.
When you add lead time to a task, work on that task will overlap work on its predecessor.

Before you can start adding lead or lag time, you need to create a dependency between the two tasks. In most cases, your dependency would point from the end of a task, the predecessor, to the beginning of another task, the successor. This is an end-to-start dependency.

One of the great features in ManagePlaces is that you can change the date of a task simply by dragging and dropping to the task to its new date. If you change the date of a 'Predecessor' task, the system will automatically update the 'Successor' tasks as well, along with task reminders. This allows you to effectively automate large parts of the project management process, saving you time and minimising the risk of human error.



Here’s how lag time looks in the Gantt chart (1 day lag time):



Here’s how lead time looks in the Gantt chart (2 days lead time):


    • Related Articles

    • How to create dependencies between tasks

      In ManagePlaces you can easily create a task dependency that is “Start after” (i.e. your new item will depend on the previous item). This is how it works: ​​ 1.1. Navigate to the gantt chart view ("Projects" > "Tasks" > "Gantt") Gantt view 1.2. You ...
    • Using the Drag 'n' Drop Gantt Chart

      When you create a project in ManagePlaces, the system will automatically generate a Drag 'n' Drop Gantt chart for you. Making changes to your project is as simple as dragging and dropping and, because the Gantt chart is fully dynamic, any changes you ...
    • How to print a Gantt chart (single or multi-page) and export in PDF

      This article will guide you through exporting your projects’ Gantt charts as well as printing in single or multi-page format.  Note that the Gantt ‘print’ feature on ManagePlaces will generate a single PDF with the current viewer’s settings (such as ...
    • How to delete tasks

      There are two simple ways to delete Tasks. You can watch our short tutorial and/or follow the steps below: ​ 1. Delete task directly from the task dashboard 1.1. Go to "Projects" > click on the three dots on the right side of the Task you want to ...
    • How to add checklists to tasks

      In ManagePlaces, you can ensure tasks are carried out consistently and according to best practice by adding checklists. This can be achieved in two easy steps. Here's how: Watch our short tutorial: Follow the steps below: 1. First create a new task ...